SWEPCO crews, in tandem with other utility professionals, worked to rebuild key infrastructure and restore power to thousands of customers in Northwest Arkansas. As of 10 a.m. Sunday, they have restored power to 91 percent of customers who can receive power in this area.

The remaining customers without power are in areas hit especially hard by the Memorial Weekend storms. That line of severe weather produced at least seven tornadoes and hurricane-strength straight-line winds.

SWEPCO’s peak outage

They are consolidating crews to concentrate on the hardest-hit areas in Rogers, Arkansas

They are consolidating crews to concentrate on the hardest-hit areas in Rogers, Arkansas. The team is united in the commitment to help rebuild the communities they call home and support customers by restoring their power as swiftly and as safely as possible.

The restoration work in the area involves complex and labor-intensive repairs. SWEPCO’s peak outage following this weather event was 19,000 customers.

With multiple utilities offering service to customers across Benton County, the overall community impact was larger with initial, combined estimates reflecting more than 50,000 of the 70,000 Benton County residents affected.

Mobilized resources

Benton County, Arkansas, population 300,000, is served by multiple electric utility providers, including SWEPCO, Carroll Electric and the City of Bentonville. At peak, there was a combined approximate outage of 94,100.

SWEPCO had a peak of around 19,000, Carroll Electric reported 65,000 and the City of Bentonville had reported a peak of 10,100. Each mobilized resources and coordinated with community pioneers and first responders to tackle the massive restoration work.

SWEPCO restored power

As of 10 a.m. Sunday, SWEPCO had successfully restored power to most customers. Work remains to restore the remaining 1,660 customers.

  • Extensive Damage - This storm caused major damage in Northwest Arkansas. SWEPCO and contract crews located more than 400 broken poles, more than 10 miles of down power lines, at least 100 damaged transformers and identified more than 750 unique repair locations.
  • Customer Alerts - Customers who have elected to receive mobile alerts should have or will soon be sent specific restoration times for their locations. They can sign up to get these alerts or log into their online SWEPCO accounts. Please note that estimated restoration times may change based on weather and other factors.
  • Customer Repairs May Be Required - Many customers are ready to have power restored, but some have damage to their homes that must be repaired before they are able to accept power.
  • Thank You - They extend heartfelt thanks to all local officials, first responders, and the Arkansas National Guard for their collaboration and support, ensuring the crews can work as quickly and safely as possible. SWEPCO remains committed to restoring power to all affected customers and appreciates the continued support and cooperation from the community.
  • Safety Reminder - To ensure the safety of both crews and the public, customers are urged to avoid areas where work is underway, not drive past flagged or coned zones, and refrain from approaching crews while they work.
  • Restoration Debris - Please note that some storm restoration debris will be left behind temporarily until pick-up activities can be scheduled following the completion of the restoration efforts.