Axpo announces the Beznau nuclear power plant (KKB) has completed refurbishment work on Unit 2 and reconnected it to the grid, following the approval of the Swiss Federal Nuclear Safety Inspectorate (ENSI).

The focus of refurbishment comprised maintenance work, recurring tests and inspections, as well as the commissioning of new systems. In addition, integral system tests were carried out as usual. Of the 121 fuel assemblies, 20 were replaced with new elements and installed in the reactor core.

Additional safety tests on Unit 2 to be conducted

During the restart, the Beznau nuclear power plant will conduct various additional safety tests on Unit 2 and gradually take up full-load operation. Unit 2 will be back to full load in about two to three days.

At times, steam will be emitted from the non-nuclear section of the plant during the restart. This does not pose any danger to human beings or the environment.

  • Related companies
  • Axpo
  • View all news from
  • Axpo

In case you missed it

Siemens & GF Team Up For AI-Driven Semiconductor Growth
Siemens & GF Team Up For AI-Driven Semiconductor Growth

Siemens and GlobalFoundries (GF) have entered a new strategic collaboration to leverage each company’s complementary AI-based capabilities to enhance performance of semicondu...

WEG Supplies Transformers For Solar Project In Colombia
WEG Supplies Transformers For Solar Project In Colombia

WEG has consolidated an important supply for one of the largest asset management firms in Latin America. A company active in sectors such as infrastructure, credit, real estate, a...

Ceolin Group Modernizes With WEG Smart Machine
Ceolin Group Modernizes With WEG Smart Machine

Ceolin Group, a benchmark in agribusiness and responsible for more than 17,000 hectares of rice production between Uruguaiana (RS), Brazil, and Argentina, adopted WEG Smart Machine...

vfd