The Arkona offshore wind farm is fully built. The joint project between E.ON and the Norwegian energy company Equinor completed the installation of the wind turbines in record time and is largely finished. According to E.ON, the 60th and last turbines were installed in the German Baltic Sea.

The construction time of just three months for 60 six-megawatt wind turbines, including loading, weather downtimes, and technical maintenance, was faster than ever before in the industry. As the company responsible for the construction and operation of Arkona, E.ON is setting a new industry standard.

the fastest installation ever

The offshore wind farm Arkona sets a benchmark for the offshore wind business in Germany and beyond"

E.ON and Equinor deserve great recognition. The construction of 60 turbines on the foundations in less than three months is the fastest installation ever achieved worldwide,” congratulates Jörg Kuhbier, Honorary Chairman of the Offshore Foundation.

I congratulate the operators on the quick finalization of the wind farm. The excellent offshore infrastructure of the port in Mukran on the island of Rügen has made its contribution to this. The offshore wind farm Arkona sets a benchmark for the offshore wind business in Germany and beyond,” emphasizes Christian Pegel, Minister for Energy, Infrastructure, and Digitization in Mecklenburg-Western Pomerania.

Safe and efficient installation

Holger Matthiesen, Project Director E.ON Climate & Renewables, “The Arkona project has completed the installation of the wind turbines safely and extremely efficiently. We are proud of this record. It is the result of excellent teamwork with our partners Siemens Gamesa, A2Sea, and Port Mukran.”

The wind farm Arkona has been producing renewable energy since September 2018. The construction of the offshore wind farm will be completed within the next few months. Arkona is scheduled to go into full operation in 2019.

Saving CO2 emissions 

The Arkona project is located 35 kilometers northeast of the island of Rügen. The wind farm will have a capacity of 385 megawatts and can theoretically supply around 400,000 households with renewable energy. The investment volume amounts to €1.2 billion.

Arkona saves up to 1.2 million tons of CO2 annually compared to conventionally generated electricity. 60 six-megawatt class turbines from Siemens have been installed. Arkona is a joint venture between E.ON and the Norwegian energy company Equinor.

Download PDF version Download PDF version

In case you missed it

Franklin Electric Hires Daniela Williams As CHRO
Franklin Electric Hires Daniela Williams As CHRO

Franklin Electric Co., Inc. announced that Daniela Williams will join its executive leadership team as Chief Human Resources Officer (CHRO), bringing a proven track record of drivi...

MILWAUKEE M12-M18 Gangbox Charger For Job Sites
MILWAUKEE M12-M18 Gangbox Charger For Job Sites

MILWAUKEE® introduces the newest addition to its charging range, the M12™-M18™ Gangbox charger, designed for charging in gangboxes and steel storage....

Copley Controls Nano HP Digital Servo Drives Release
Copley Controls Nano HP Digital Servo Drives Release

Copley Controls, a global pioneer in the motion control industry, announces the release of its Nano High Power (Nano HP) and Nano Plus High Power (Plus-HP) digital servo drives for...

vfd