Kunliulong project is an important project to implement the West to East power transmission and absorb clean energy in China. It is also a major science and technology pilot project in the power industry.

The commissioning of the project will further optimize the energy structure of the five southern provinces and help to achieve the goal of carbon peak and neutralization, which is of great strategic significance.

Kunliulong project

The project will span four provinces, including Yunnan, Guizhou, Guangxi and Guangdong

Relying on Wudongde Hydropower Station, Kunliulong project will build a new ± 800kV UHVDC transmission line with a total length of 1452km, and three ± 800kV high voltage converter stations in Kunbei, Liuzhouand Longmen.

The project will span four provinces, including Yunnan, Guizhou, Guangxi and Guangdong. It will transport green and clean hydropower from Yunnan to Guangxi power load center and Guangdong, Hong Kong and Macao Bay area.

Boosting Transmission Capacity

After the project is put into operation, the total transmission capacity will reach 8GW, and 33TWh of clean hydropower will be transmitted annually. 

Kunliulong project adopts hybrid transmission technology of LCC-HVDC and VSC-HVDC for the first time in the world, which provides valuable experience for the development of world power grid.

As the main supplier of Kunliulong project, NR has provided a complete set of core equipment included  HVDC control protection system, converter valve, water cooling system, DC measurement, stability control system, DC de-icing and AC protection equipment.

Overcoming Technical Hurdles

NR has successively overcome the coordination of LCC-HVDC and VSC-HVDC, fault self-clearing

Kunliulong project has many technical challenges and great difficulty in tackling key problems.

NR has successively overcome the coordination of LCC-HVDC and VSC-HVDC, fault self-clearing and high-speed restart of VSC-HVDC overhead line, balance control of VSC-HVDC series valve group, low delay 800kV DC optical current transformer and coordination and cooperation among multi terminal DC stability control systems.

NR's strong support for The Kunliulong project

In the process of project construction, NR continued to provide strong support for the construction of Kunliulong project.

In the face of severe epidemic prevention and control situation, on the basis of strict implementation of epidemic prevention measures, NR accurately and efficiently returned to work and production, completed the production,  supply and commission the system on schedule.

Next-Gen Transmission

The commissioning of Kunliulong project marks that the technical level of UHVDC transmission  has been upgraded to a new level. As an important participant in the Kunliulong project, NR has fully demonstrated its leading technology level in the field of LCC-HVDC and VSC-HVDC transmission.

NR will continuously develop new technologies and expand new applications, provide customers with advanced technologies, reliable products and high-quality services, and serve the power industry.

Download PDF version Download PDF version

In case you missed it

Alva's SlimTorq & Copley Servo Drive Exhibited At Automatica 2025
Alva's SlimTorq & Copley Servo Drive Exhibited At Automatica 2025

ALVA Industries (Alva) and Copley Controls are partnering to present a joint live demonstration at Automatica 2025, showcasing the integration of Alva’s SlimTorq™ frame...

Comau Wins 2025 Sustainability Award For Green Innovation
Comau Wins 2025 Sustainability Award For Green Innovation

Comau was awarded the 2025 Sustainability Award at the 14th Panda d’Oro Ceremony on June 14. Hosted by the China-Italy Chamber of Commerce (CICC) with support from the Embas...

Smart Tech Boosts Hospitality Energy Efficiency
Smart Tech Boosts Hospitality Energy Efficiency

With a 12% year-on-year growth in revenue per available room (RevPAR) anticipated this summer, South Africa’s hospitality sector is preparing for a lucrative festiv...

vfd