At 5:00 a.m. local time on August 22, 2019, the massive load test of the ±800kV UHV DC transmission project for Belo Monte Dam II of Brazil was successfully completed. So far, the project has completed all system tests and has been provided the conditions for commercial operation.

During the field commissioning, the UHVDC converter valve, DC control & protection system, DC measuring equipment, power grid stability control system, and other core equipment supplied by NR have been in good and stable condition.

Electricity from hydro power resources

The Belo Monte Dam (formerly known as Kararaô) is a hydroelectric power plant currently under construction on the Xingu River in the state of Pará, Brazil. The planned installed capacity would be 11,233 MW, which would make it the second-largest hydroelectric dam complex in Brazil and the fourth-largest in the world. 

In Phase II, a ±800kV UHVDC link with a distance of 2518km has been built. It will be capable of transporting 4000 MW of electricity from hydro power resources in Amazon Valley in the northwest of Brazil to load centers in the southeast part of Brazil, such as Rio De Janeiro and São Paulo.

NR power stability control system

The PCS-8600 UHVDC single pole 12-pulse converter valve is the world’s highest voltage level

NR supply scope includes converter valves, UHVDC control and protection system, UHVDC current and voltage measurement equipment, and power stability control system.

The PCS-8600 UHVDC single pole 12-pulse converter valve is of world’s highest voltage level. It has been certified to the international standard by KEMA. 

The UHVDC control and protection system provides coordination, control, and shared grounding with the existing UHVDC link. The highly precise DC measurement equipment and power stability control system will ensure fast step response and safe operation of AC/DC interconnected grids.

UHVDC transmission project

NR Electric, as a power stability expert, is a pioneering power system solution provider across the world. Belo Monte Dam Phase II ± 800kV UHVDC transmission project in Brazil is the first UHV transmission project independently won by the State Grid Corporation of China.

The successful implementation of the project has enabled the world's pioneering Chinese UHV technology to go abroad and will make a great contribution to local people constantly.

Download PDF version Download PDF version

In case you missed it

Amphenol PowerLok Connectors For EV & Renewable Systems
Amphenol PowerLok Connectors For EV & Renewable Systems

TME's product range has been expanded to include PowerLok power connectors from Amphenol GEC. This is a new offering from a renowned supplier, primarily aimed at manufacturers and...

Emerson Achieves Major Energy Savings In Wisconsin
Emerson Achieves Major Energy Savings In Wisconsin

Emerson announced that its Appleton Group iron casting facility has received a 2025 Energy Excellence Award from Focus on Energy®. The award recognizes companies in Wisconsin t...

Aceleron Debuts OffGen At Solar & Storage Live Expo
Aceleron Debuts OffGen At Solar & Storage Live Expo

Solar & Storage Live, as well as EMEX expo, sees more than 150 exhibitors from across the globe, featuring new ways of thinking and novel partnerships, to generate solutions to...

vfd