  • Wasatch Electric remodeled historic building with cutting-edge electrical systems in Salt Lake City.
  • Completed one-night electrical cut-over while maintaining tenant operations to modernize century-old building.
  • Installed 16,000 feet conduit, 15,000 feet MC Cable, 98,000 feet wire in renovation project.

The renovation of the historic Hines-Kearns Building in downtown Salt Lake City saw Wasatch Electric successfully deliver critical electrical distribution and lighting services.

Despite the challenges posed by the occupancy of the tenants throughout the upgrade, the project benefitted from meticulous planning and safety protocols, ensuring minimal disruption.

Innovative Electrical Systems

This over 100-year-old office landmark, which holds a place on the National Register of Historic Places, underwent significant modernization to meet contemporary standards. Upgrades included revamping the elevators, overhauling the entire HVAC system, and enhancing restrooms.

New amenities such as a wellness and fitness center, a large breakroom, and an outdoor courtyard were added, along with modern electrical systems. The imperative was to maintain seamless business operations in this pivotal Salt Lake business hub during the updates.

Electrical Distribution System Renovation

In order to prevent tenant disruption, a parallel electrical distribution setup was constructed alongside the operational existing system, a process that significantly limited workspace but was essential for the building's continuous operation.

This required extensive months of careful planning and coordination, culminating in a successful overnight transition from the old to the new system.

Comprehensive Project Scope

The project encompassed various scopes, including a 200-amp switchboard installation and the integration of five new panel boards. Additionally, 27 existing panel boards were refed. The state-of-the-art lighting systems, alongside advanced controls and fixtures, were installed throughout common areas on all ten floors.

The task also involved removing outdated distribution equipment and circuits and setting up approximately 16,000 feet of conduit, 15,000 feet of MC Cable, and 98,000 feet of wire.

In case you missed it

Siemens & GF Team Up For AI-Driven Semiconductor Growth
Siemens & GF Team Up For AI-Driven Semiconductor Growth

Siemens and GlobalFoundries (GF) have entered a new strategic collaboration to leverage each company’s complementary AI-based capabilities to enhance performance of semicondu...

WEG Supplies Transformers For Solar Project In Colombia
WEG Supplies Transformers For Solar Project In Colombia

WEG has consolidated an important supply for one of the largest asset management firms in Latin America. A company active in sectors such as infrastructure, credit, real estate, a...

Ceolin Group Modernizes With WEG Smart Machine
Ceolin Group Modernizes With WEG Smart Machine

Ceolin Group, a benchmark in agribusiness and responsible for more than 17,000 hectares of rice production between Uruguaiana (RS), Brazil, and Argentina, adopted WEG Smart Machine...

vfd