Prysmian Group, the pioneer in the energy and telecom cable systems industry, has been awarded a new contract by Ørsted Wind Power A/S to supply inter-array submarine cables for the Hornsea 3 offshore wind farm, located 160 km off the Yorkshire coast, UK.

Once constructed, it will be able to supply well over 3 million homes with green, renewable electricity. Under the contract, subject to Ørsted taking a Final Investment Decision on Hornsea 3, Prysmian Group will be responsible for the design, manufacture, supply, termination, and testing of the inter–array submarine cable system that will connect the wind turbines and the offshore converter station. 

Delivery time

The project involves approximately 280 km of 66 kV inter-array cables with XLPE insulation

The project involves approximately 280 km of 66 kV inter-array cables with XLPE insulation, which will cover approximately 50% of the overall wind farm’s requirements.

All the submarine cable cores will be produced at the Group’s centers of excellence located in Montereau and Gron, France, while the armoring and assembling processes will be performed at the plant in Nordenham, Germany. The cables are due to be delivered in 2026.

submarine cable systems

This award reflects Ørsted’s trust in Prysmian’s capabilities to meet the increasing need for submarine cable systems to support the energy transition to smarter and greener power grids,” stated Juliano De Mello, Sales Team Manager Offshore Wind, Prysmian Group.

Juliano De Mello adds, "We are very pleased and proud for having been chosen again to undertake such a challenging project supporting Ørsted to meet the UK Government’s ambition to deliver 50 GW of offshore wind power by 2030 as part of the British Energy Security Strategy. Thanks to our technological and state-of-the-art products and solutions, we will ensure a safe and reliable energy supply to the communities of the area."

66 kV inter-array submarine cable system

After working successfully with Prysmian on the Hornsea 2 project, we are delighted to work together again"

Previously, in 2018, Ørsted had awarded Prysmian Group a contract to design, manufacture, supply, and test a 66 kV inter–array submarine cable system for the Hornsea 2 offshore wind farm, connecting 110 of the 165 wind turbines and the offshore substation platform.

Luke Bridgman, Senior Project Director for Hornsea 3, commented, “After working successfully with Prysmian on the Hornsea 2 project, we are delighted to work together again on Hornsea 3."

low-cost clean energy

Luke Bridgman adds, "The project represents another leap forward in terms of the size and scale of offshore wind farms, and collaborations with world-class manufacturers such as Prysmian are crucial to executing the project successfully."

He concludes, "Prysmian shares our commitment to providing further sources of low-cost clean energy and we look forward to another great cooperation.”

Download PDF version Download PDF version

In case you missed it

Karenann Terrell Joins Eaton Board, Boosting Digital Expertise
Karenann Terrell Joins Eaton Board, Boosting Digital Expertise

Intelligent power management company Eaton announces that Karenann Terrell has been elected to the company’s Board of Directors effective July 24, 2024. Terrell is the retir...

EPSRC Funds Cutting-Edge Semiconductor Research At Surrey
EPSRC Funds Cutting-Edge Semiconductor Research At Surrey

A brand-new 1.25 million volts (MV) implanter will spark cutting-edge research and innovation in semiconductor and quantum technologies, say scientists at the University of Surrey....

Eaton Recognized For Disability Inclusion Across Three Countries
Eaton Recognized For Disability Inclusion Across Three Countries

Intelligent power management company Eaton announced its commitment to inclusive strategies and programming for people with disabilities and has earned high scores on three Disabil...

vfd